Judicial Branch of the Virgin Islands Commencement of Phase II

Virgin Islands News

Public Notice

Judicial Branch of the Virgin Islands Commencement of Phase II – Roof Replacement and Office Expansion Project – Superior Court of the Virgin Islands R.H. Amphlett Leader Justice Complex located at No. 1 Kingshill Hall of Justice, St. Croix VI, 00850

The Judicial Branch of the Virgin Islands hereby notifies the general public of the commencement of Phase II of the Roof Replacement and Office Expansion Project at the Superior Court of the Virgin Islands RH Amphlett Leader Justice Complex located at No. 1 Kingshill Hall of Justice, St. Croix, VI 00850. Phase II is  scheduled to commence on Monday, July 28, 2025.

Phase II will include the facility improvements such as roof hardening with the installation of a roof hugger retrofitted system, construction of a space frame over the central courtyard and ballistic proof entry curtain wall enclosure.  The space frame will incorporate translucent corrugated hurricane panels, impact resistant glass, and a louvered ventilation system to enhance durability and energy efficiency while expanding the interior useable footprint of the court.  The court will also maximize interior space through a redesign of administrative offices, construction of new ADA-compliant restrooms, a modernized employee lounge, and the addition of a concrete swale to improve exterior drainage and mitigate flood impact. Construction activities will take place Monday through Saturday between the hours of 6 am to 6 pm. The project will not impact traffic flow and there will be no public facing site changes.  The Judicial Branch appreciates the community’s cooperation as we work to enhance our facilities in service to the people of the Virgin Islands.

For more information, contact:
Regina Petersen, Administrator of Courts
Judicial Branch of the Virgin Islands
P.O. Box 590
St. Thomas, U.S. Virgin islands 00804
Tel: (340)774-2237   Fax: (340) 774-2258  TTY (340) 693-4118
Regina.Petersen@vicourts.org

Read More

St. Croix Source

Legal Notice, Public Notices, Uncategorized 

Virgin Islands News - News.VI

Share the Post:

Related Posts

Virgin Islands News

Decade-Long Stadium Project Faces Scrutiny Over Costs, Delays, and Design Changes

After months of delays and missed hearings, several key officials and the contractor behind the Paul E. Joseph Stadium project finally appeared before the Senate – some under subpoena – on Friday to explain why, more than a decade after the first contract was signed, the stadium remains unfinished.
At the heart of the testimony was a pattern of escalating costs and shifting designs. The project was initially contracted to GEC, LLC in December 2014 for $20 million, with an anticipated completion date of June 2017. According to GEC Managing Member John Wessel, the original design called for a larger stadium on the existing footprint, incorporating the reuse of the stadium’s concrete outfield wall and lights. But that plan changed just months later, when then-Gov. Kenneth Mapp issued a stop-work order in early 2015, requesting a revised design that relocated the stadium into a FEMA-designated floodway.
That decision, Wessel said, created years of complications. “Had we not been required to redesign the foundations due to the floodway relocation, the project likely would have been completed by 2017,” Wessel told senators. Instead, FEMA-mandated design changes, including deep pile foundations, led to significant delays and additional permitting hurdles.
By 2019, escalating costs prompted Gov. Albert Bryan Jr. to order a redesign aimed at scaling back the project to control spending, testifiers said. Wessel testified that the design changes requested by the Bryan administration eliminated features from the original plan, including the stadium’s announcer’s box and a planned scoreboard. “I follow what the client tells me to do,” Wessel said when pressed by Sen. Marise James about why he hadn’t objected to removing key stadium elements. “As a design-build contractor, I deliver what the owner requests.”
The result of these cumulative changes: 24 change orders and two supplemental contracts totaling over $9 million on top of the original contract price. According to Property and Procurement Commissioner Lisa Alejandro, the department processed two formal supplemental contracts with GEC: the first in February 2022 for $4.1 million, and the second in September 2024 for $5.124 million.
These latest additions, authorized under Act 8781, included scope elements that were originally planned but later removed and subsequently reinstated: perimeter fencing, a concrete outfield wall, fiber optic utility relocation, a 750 kW generator, WTJX communications stations, and the relocation of sewer lines around Terrence Martin Field. Also added was revised site lighting using solar technology, and several design revisions required to comply with FEMA’s flood zone regulations. Wessel explained that many of these additions were necessary for operational functionality, including the outfield wall and generator.
“Effectively, after removing features to save costs, the government decided to restore much of what had been taken out—though at a higher price,” Wessel noted.
Permitting delays compounded the problem. Planning and Natural Resources Commissioner Jean-Pierre Oriol confirmed that FEMA approvals, including a Conditional Letter of Map Revision (CLOMR), were not secured until early 2021. DPNR had to issue multiple permits at different stages—demolition, earthwork, foundation, and utilities—with Oriol noting, “the stadium’s relocation into the floodway drove much of the delay.”
Meanwhile, Public Works Commissioner Derek Gabriel placed current project completion at “70 to 75 percent” under questioning from Sen. Marvin Blyden. Gabriel detailed that current work includes roofing, mechanical and electrical systems, and construction of Terrence Martin Field’s foundation. He acknowledged that the project’s oversight rests primarily with Public Works, though coordinated review of change orders involved Property and Procurement, the Office of Disaster Recovery, and the Department of Sports, Parks, and Recreation.
DSPR Commissioner Nominee Vincent Roberts reiterated the department’s frustration with delays, emphasizing the need for a facility capable of supporting youth leagues, cultural festivals, and sports tourism initiatives. Roberts noted that DSPR’s role as the project’s end-user had required constant engagement to ensure the stadium met practical operational standards. “We also raise concerns when project delays or design changes threaten to compromise the stadium’s intended use,” he told lawmakers.
As for the stadium’s completion, Wessel cautioned that while current construction continues, additional funding may be required to cover delay-related costs—funds not yet identified by the government. “Funding for accumulated delay costs remains unresolved,” he testified.
Originally envisioned as a $20 million project with a 30-month schedule, the Paul E. Joseph Stadium redevelopment has now stretched to an estimated $35 million-plus undertaking with a revised completion date of December 25, 2025. Whether that date holds, lawmakers heard repeatedly, depends on resolving the project’s final design adjustments and funding gaps.

Read More